650 Florida cases classified under this topic, plus 572 listed through its narrower topics · sorted by citation count · see the citation graph · browse and sort
-
622 F.2d 243·
6th Cir.·
1980-05-20
·cited 18×
The court held that a potential mechanic's lien constitutes a security interest under TILA, requiring disclosure, and that the right to rescind is not barred by the statute of limitations for damages. However, rescission is conditioned on the debtor returning the reasonable value
-
371 So. 2d 559·
Fla. 4th DCA·
1979-05-31
·cited 18×
Tuttle/White Constructors and its surety appealed a judgment awarding Hughes Supply payment for materials supplied to a subcontractor on a construction project. The court reversed and remanded, holding that while Hughes failed to give timely notice for priority lien status, it st
-
362 So. 2d 1014·
Fla. 1st DCA·
1978-10-03
·cited 18×
In a mechanics' lien foreclosure case with counterclaim, the trial court denied attorney's fees to both parties. The appellate court reversed, holding that the defendant who successfully resisted the lien foreclosure was the prevailing party entitled to recover reasonable attorne
-
323 So. 2d 684·
Fla. 4th DCA·
1975-12-05
·cited 18×
A general contractor sought an equitable lien on undisbursed construction loan funds after the owner breached a construction loan agreement and the lender refused to disburse the final payment due. The court held that the contractor was entitled to an equitable lien on the specif
-
292 So. 2d 415·
Fla. 2d DCA·
1974-03-29
·cited 18×
A subcontractor (Nunamaker) sued its contractor (Knowles) for payment and sought to impose a mechanics' lien on the owners' (Trustees') land. The court held that Nunamaker's failure to timely serve notice of intent to claim a lien on the owners precluded the lien, even though one
-
Foxbilt Electric sought to foreclose a mechanic's lien against the Belefants, who countered claiming damages for dissatisfactory work. The trial court awarded attorney's fees to the defendants despite finding in plaintiff's favor on the lien foreclosure. The appellate court rever
-
Oven Development Corporation appealed jury verdicts in three consolidated construction contract cases where homeowners prevailed against Oven's mechanic's lien foreclosure claims and counterclaims for breach of contract. The First District Court of Appeal reversed, holding that O
-
468 F.2d 14·
10th Cir.·
1972-10-16
·cited 18×
The court held that the federal "first in time, first in right" rule, requiring choateness, governs the priority of liens when the United States is involved, and state law cannot subordinate a federal lien by allowing subsequently filed mechanics' liens to relate back.
-
Lion Oil Company appeals from a judgment awarding attorney's fees to Tamarac Lakes after Lion Oil dismissed its mechanic's lien foreclosure action against Tamarac Lakes. The court affirmed, holding that the trial court properly retained jurisdiction to award reasonable attorney's
-
Remington Construction appealed a foreclosure decree on a mechanic's lien after their answer was struck for failure to respond to interrogatories without a prior court order. The court reversed, holding that Florida Rules of Civil Procedure require a trial court to enter an expli
-
338 F.2d 826·
9th Cir.·
1964-11-17
·cited 18×
The court held that marshaling of assets should not be ordered if it entails a risk of loss to the senior creditor, even if the loss is not certain.
-
297 F.2d 70·
1st Cir.·
1961-12-08
·cited 18×
A subcontractor may recover the reasonable value of labor and materials furnished, including a reasonable profit on extras actually supplied at the contractor's direction, but may not recover lost profits on unperformed portions of the contract under the Miller Act, as such damag
-
60 So. 2d 15·
Fla.·
1952-07-15
·cited 18×
The Supreme Court of Florida held that a contractor who failed to obtain a required city license could still recover the reasonable value of labor and materials furnished on a quantum meruit basis, even though the contract was terminated. The court reversed a lower court's dismis
-
43 So.2d 335·
Fla.·
1949-11-01
·cited 18×
This case concerns whether a materialman can claim a lien on real property for specially fabricated steel that was not delivered to the construction site, but stored elsewhere, awaiting shipping instructions from the general contractor. The court held that such a lien could not b
-
Southern Paint Manufacturing Co. sought to enforce a materialman's lien against a property owner who had paid the contractor in full without receiving a sworn statement of payment from the contractor. The Florida Supreme Court affirmed dismissal of the complaint, holding that mat
-
637 So. 2d 5·
Fla. 3d DCA·
1994-05-03
·cited 17×
The court held that a lis pendens cannot be based on an unsecured promissory note or an equitable lien claim that is not founded upon a duly recorded instrument.
-
578 So. 2d 388·
Fla. 3d DCA·
1991-04-16
·cited 17×
The trial court erred by abating a mechanic's lien action and granting additional time to retain counsel, as the statutory time limits for showing cause were not met.
-
The court held that the district court's order affirming liability but remanding for further factual development on attorneys' fees was not a final decision, and thus the appeal was dismissed for lack of jurisdiction.
-
825 F.2d 692·
2d Cir.·
1987-08-04
·cited 17×
Bankruptcy courts must give preclusive effect to state court default judgments to the same extent as the rendering state would, absent fraud, collusion, or lack of jurisdiction. The bankruptcy court's equitable powers do not permit it to disregard a lawfully obtained default judg
-
VINCI Development Company sued for breach of contract and mechanic's lien foreclosure; the owner counterclaimed for damages. The jury awarded VINCI $10,791.43 for work performed, but the trial court found VINCI's lien fraudulently exaggerated and awarded the owner punitive damage
-
500 So. 2d 204·
Fla. 1st DCA·
1986-09-16
·cited 17×
The court affirmed a lower court's decision to deny a motion to dismiss, holding that a contractual clause selecting a specific county in Texas for all litigation arising from a Florida subcontract was unenforceable. The court found that enforcing the clause would violate strong
-
KMS of Florida Corp. appeals a cost and attorney's fee award to the prevailing defendant in a mechanic's lien foreclosure action. The court reverses the award of expert witness fees and bond-related costs, finding no legal basis for these items under Florida law.
-
The court held that HUD succeeded to the mortgagee's duties under the building loan agreement, and the surety succeeded to the subcontractors' rights, allowing recovery of retainage.
-
244 So. 2d 528·
Fla. 2d DCA·
1970-12-11
·cited 17×
A subcontractor seeks to enforce a mechanic's lien against property owners after the general contractor failed to pay it, despite receiving final payment. The court addresses whether notice to the owner under Florida's mechanic's lien statute becomes effective upon mailing or rec
-
219 So. 2d 475·
Fla. 3d DCA·
1969-02-25
·cited 17×
CECO Corporation, a sub-subcontractor, sued to foreclose a mechanics' lien against property for labor and materials furnished in apartment construction. The trial court dismissed the complaint, holding that Florida's Mechanics' Lien Act does not provide liens to sub-subcontractor
-
197 So. 2d 13·
Fla. 3d DCA·
1967-03-28
·cited 17×
A contractor must provide the owner with a sworn affidavit stating all lienors have been paid before filing suit to enforce a mechanic's lien.
-
The Florida Supreme Court affirmed that a mortgagee's lien on a vehicle takes priority over a repair garage's mechanic's lien when the mortgage was recorded before the repair work was performed. The court rejected the common law principle that mechanics' liens are universally sup
-
20 Fla. 937·
Fla.·
1884-06-01
·cited 17×
This case examines whether a married woman's separate statutory property can be subjected to a mechanic's lien for materials furnished in building on her land. The court held that the mechanic's lien statute did not grant married women the power to enter into contracts that would
-
905 So. 2d 76·
Fla.·
2005-06-09
·cited 16×
The Florida Bar disciplined attorney Daryl James Brown for ethical violations arising from his conduct as president of a real estate development corporation that engaged in 'double pledging' of a certificate of deposit. Brown represented to a surety company that the CD would serv
-
The Supreme Court of Florida held that an order denying a motion to dismiss based on untimely service under rule 1.070(c) is not a proper subject for interlocutory appeal under rule 9.130(a)(3)(C)(i) because the amended rule should apply retroactively and does not expand the cate
-
The court held that the discharge of a lis pendens was improper because the surety bond, which was the basis for the discharge, was never offered or considered by the lower court.
-
655 F.2d 1047·
Ct. Cl.·
1981-06-17
·cited 16×
The United States did not enter into an express or implied contract with the contractor by virtue of HUD's intimate involvement in supervising a federally insured housing project, as the sovereign acts of insuring the mortgage and accepting its assignment do not create contractua
-
The court held that genuine issues of material fact existed regarding the timeliness of the mechanic's lien filing and the nature of the final work performed, precluding summary judgment.
-
618 F.2d 611·
9th Cir.·
1980-05-13
·cited 16×
The court held that California Civil Code § 3264 bars a contractor's claims for equitable lien and third-party beneficiary status against a mortgage lender, and that state law governs other claims like inducing breach of contract and unjust enrichment.
-
A trial court cannot include costs and attorney fees from a prior, unrelated lawsuit in a stay order under Fla.R.Civ.P. 1.420(d) when the claims in the two suits are not the same.
-
569 F.2d 87·
D.C. Cir.·
1977-11-30
·cited 16×
The court held that Joint Venture and Chevy Chase were not third-party beneficiaries of the construction contract, but that Limited Partnership was a successor-in-interest to Winthrop and could sue for breach of contract.
-
348 So. 2d 1202·
Fla. 4th DCA·
1977-07-22
·cited 16×
Leader Mortgage Company appealed a judgment foreclosing a mechanic's lien filed by Rickards Electric Service. The court affirmed the money judgment against Leader and co-defendant Bruscino Construction Company but reversed the portion imposing a lien on real estate owned by third
-
Associated Plastics supplied paint to a subcontractor on a condominium project and filed a mechanic's lien against the property owner, Saul J. Morgan Enterprises. The trial court entered judgment for Associated, but the appellate court reversed, finding that Associated failed to
-
Mid-State Contractors appeals dismissal of its mechanics' lien foreclosure action based on a technical deficiency in the lien claim's specification of the amount owed. The court holds that substantial compliance with statutory requirements is sufficient, and remands for determina
-
335 So. 2d 623·
Fla. 2d DCA·
1976-07-28
·cited 16×
Hamilton appeals the trial court's denial of their motion to dismiss a mechanic's lien foreclosure action as time-barred. The court held that a prior dismissal for lack of prosecution did not toll the one-year statute of limitations for filing a lien foreclosure suit, and therefo
-
The court held that the record was sufficient to justify the bankruptcy judge's approval of the compromise, and that the bankruptcy judge did not abuse his discretion.
-
A contractor sought to foreclose a mechanic's lien against a property owner and property management company for improvements made by a lessee tenant. The trial court denied the lien claim, and the appellate court affirmed, holding that the contractor failed to comply with statuto
-
278 So. 2d 282·
Fla.·
1973-05-23
·cited 16×
The Florida Supreme Court resolved a certified question of great public interest concerning whether filing an amended mechanics' lien tolls the 60-day deadline to file suit under Florida's lien statute. The Court held that amendments do not toll the statutory time period, and a l
-
Contractors sued to foreclose a mechanics' lien for concrete work. The trial court granted summary judgment against them based on alleged defects in notice timing and lack of occupational license. The appellate court reversed, holding that the late notice did not vitiate the lien
-
In this mechanic's lien foreclosure case, the Florida District Court of Appeal reversed a summary judgment against Travelers Indemnity Co. (a payment bond surety) because genuine issues of material fact existed regarding whether funds remained after payment of priority lienors. T
-
232 So. 2d 441·
Fla. 4th DCA·
1970-03-13
·cited 16×
Motz Construction Corp. appealed a judgment dismissing its mechanic's lien foreclosure action where the lien claim was filed under the individual name 'George J. Motz' rather than the corporate name 'George J. Motz Construction Corp.' The court reversed, holding that substantial
-
411 F.2d 1246·
Ct. Cl.·
1969-06-20
·cited 16×
The court held that the plaintiff's claims for Fifth Amendment 'taking' of plans and for equitable lien against retained funds were without merit.
-
The court held that a materialman must prove either incorporation of materials into the improvement or special fabrication for it, and delivery to the site is only prima facie evidence of incorporation.
-
388 F.2d 156·
4th Cir.·
1967-12-04
·cited 16×
When a federal agency's subordinated claim, a prior mortgage, and a mechanic's lien compete for sale proceeds of insolvent property, federal law determines that the prior mortgage is paid first, the federal agency receives the remainder up to its loan amount, and state law then g
-
200 So. 2d 579·
Fla. 3d DCA·
1967-06-13
·cited 16×
Morris and Esher, a general contractor, sought to foreclose a mechanics' lien that included amounts owed to unpaid subcontractors. The court reversed in part and affirmed in part, holding that a general contractor may include unpaid subcontractor claims in a lien foreclosure comp