650 Florida cases classified under this topic, plus 572 listed through its narrower topics · sorted by citation count · see the citation graph · browse and sort
-
312 F.2d 603·
10th Cir.·
1962-12-21
·cited 16×
The court held that the trial court erred by failing to make specific findings of fact as required by Rule 52(a) when the facts were disputed and unclear.
-
Property owners appealed a lower court decision imposing a mechanic's lien on their real property for wall-to-wall carpeting supplied to their lessee's apartment building. The Florida appellate court reversed, holding that carpeting is not an 'improvement' under the Florida Mecha
-
305 F.2d 363·
10th Cir.·
1962-06-15
·cited 16×
The Miller Act does not apply to payment bonds furnished in connection with military housing projects under the Capehart Act because such projects are privately financed and constructed until the government assumes control upon completion, and therefore are not public works of th
-
142 So. 2d 346·
Fla. 1st DCA·
1962-06-12
·cited 16×
Settlement negotiations and confusion arising from law firm dissolution do not constitute 'good cause' under Florida Statute Section 45.19 to reinstate an action dismissed for want of prosecution. Any petition for reinstatement must allege facts constituting good cause that the t
-
275 F.2d 106·
10th Cir.·
1960-01-23
·cited 16×
The court held that the SBA's chattel mortgage had priority over the mechanic's lien because federal law governs, and the mortgage did not contain language implying authorization for repairs.
-
108 So. 2d 896·
Fla. 1st DCA·
1959-02-17
·cited 16×
A bulldozer operator sought to foreclose a mechanics' lien against a land company for clearing work performed on leased property. The court affirmed the dismissal, holding that the lien statute did not apply because the lease did not require the lessee to perform the clearing wor
-
94 So. 2d 355·
Fla.·
1957-04-10
·cited 16×
The Florida Supreme Court struck down a statute (Chapter 28243, Acts of 1953) that required owners of construction contracts worth $3,000 or more to either obtain a performance bond or withhold 20% of payments, and that imposed personal liability and liens for all outstanding con
-
84 So. 2d 32·
Fla.·
1955-12-14
·cited 16×
Wood appeals a dismissal of his complaint seeking declaration of a mechanic's lien for labor and materials furnished to improve Wilson's homestead property. The Florida Supreme Court affirmed the dismissal, holding that an action to enforce a materialman's lien must comply with s
-
224 F.2d 232·
2d Cir.·
1955-06-29
·cited 16×
A state-created trust fund for subcontractors does not divest the contractor of property interest for federal tax purposes, and the mechanic's lien is inchoate until perfected by legal action.
-
127 F.2d 652·
6th Cir.·
1942-04-16
·cited 16×
A mortgage recorded after construction began, without a covenant authorizing the mortgagee to pay laborers and materialmen, does not entitle the mortgagee to share equally with mechanic's lien claimants in bankruptcy proceeds.
-
This case concerns a materialman's lien on a married woman's separate property. The court affirmed the lower court's decision, finding that the married woman was estopped from denying agency and that the materialman had substantially complied with the Uniform Mechanics' Lien Act
-
53 Fla. 255·
Fla.·
1907-01-01
·cited 16×
Mechanics lien case where subcontractors sued the building owner R.K. Mullikin for unpaid labor and materials. The Florida Supreme Court reversed the judgment, holding that subcontractors without direct privity to the owner must serve written notice on the owner and can only enfo
-
Global Xtreme challenges an attorney's fees award to Advanced Aircraft Center based on sections 57.105 and 713.29, Florida Statutes. The appellate court reversed, holding that Advanced failed to comply with the strict notice requirements of section 57.105 and that section 713.29
-
761 So. 2d 1221·
Fla. 2d DCA·
2000-06-30
·cited 15×
A Florida appellate court reversed a trial court's denial of a motion to stay litigation pending arbitration, holding that a subcontract between a general contractor and subcontractor contained a valid and enforceable mandatory arbitration clause governed by Florida law, despite
-
Homeowner Terrell Martin appealed a trial court judgment finding her in breach of a construction contract with Jack Yanks Construction Company and denying her punitive damages claim for a fraudulent lien. The Third District Court of Appeal reversed, holding that the parties' agre
-
Moore Handley appeals an order denying its motion to dismiss a counterclaim filed by Major Realty in a mechanic's lien foreclosure action. The appellate court partially reversed, holding that the restitution count stated a valid cause of action but the fraud count failed to alleg
-
335 So. 2d 842·
Fla. 4th DCA·
1976-07-02
·cited 15×
This case involves a subcontractor seeking payment on a construction bond after the general contractor failed to pay. The court affirmed a summary judgment in favor of the subcontractor, holding that the bond, which purported to protect against mechanics' liens, must be construed
-
332 So. 2d 663·
Fla. 2d DCA·
1976-06-02
·cited 15×
Florida Steel Corporation sought to garnish judgment proceeds owed to a contractor defendant pending appeal of an unliquidated contract judgment. The court held that while a superseded judgment cannot be garnished during appeal, garnishment proceedings should be stayed rather tha
-
253 So. 2d 900·
Fla. 3d DCA·
1971-10-12
·cited 15×
The court held that an interlocutory appeal was proper, the counterclaim for fraudulent lien was properly dismissed for lack of particularity, and the landowner was not the prevailing party entitled to attorney's fees.
-
77 So. 2d 632·
Fla.·
1954-07-19
·cited 15×
-
In this second appeal concerning foreclosure and redemption rights, the Florida Supreme Court addresses whether a junior mortgagee can compel an accounting of rents and profits from a successor-in-title who obtained property through foreclosure of a senior mechanic's lien. The co
-
115 Fla. 293·
Fla.·
1933-06-23
·cited 15×
A Virginia corporation foreclosed a mechanic's lien on Florida property for construction work performed while the corporation was not qualified to do business in Florida. The court held that foreign corporations cannot acquire statutory mechanic's liens while illegally doing busi
-
This case concerns the priority of a mechanic's lien foreclosure over a subsequent mortgage assignment. The Florida Supreme Court reaffirmed its prior holding in Sandquist & Snow, Inc. v. Kellogg that a mechanic's lien holder may foreclose against only the fee owner within the st
-
Taylor sought to enforce a materialman's and laborer's lien against real property owned by Cheney Development Corporation for dredging and filling work performed under a contract with Ferroman Properties, Inc., the lessee. The Florida Supreme Court reversed the trial court's deni
-
This case involves a materialman's attempt to foreclose a lien for construction materials. The court affirmed the lower court's decision, finding that the materialman failed to establish the property owner as a principal debtor and that any errors in excluding evidence were harml
-
36 Fla. 660·
Fla.·
1895-06-01
·cited 15×
James L. Clarkson appealed a decree establishing that a mechanic's lien assigned to the appellees took priority over his subsequent mortgage interest on property in Kissimmee, Florida. The Florida Supreme Court affirmed, holding that statutory mechanic's liens are assignable and
-
A contractor filed a fraudulent construction lien by including nonexistent workers' compensation insurance premiums in the amount claimed. The appellate court reversed the trial court's judgment foreclosing the lien, finding the lien fraudulent and unenforceable under Florida's c
-
Kenmark Construction appeals a foreclosure judgment where the trial court ruled in Kenmark's favor on its construction lien claim but denied attorneys' fees to both parties. The Florida Second District Court of Appeal reversed, holding that Kenmark, as the prevailing party on sig
-
National Constructors appeals a trial court judgment finding it breached its contract with the Ellenbergs for hurricane damage repairs and awarding the Ellenbergs attorney's fees as the prevailing party. The appellate court vacates and remands because the trial court failed to ma
-
Patricia Heidle appeals a trial court's denial of attorney's fees after successfully defending against S & S's mechanic's lien foreclosure action through a dismissal for lack of prosecution. The appellate court reverses, holding that Heidle was the prevailing party and is entitle
-
907 F.2d 732·
7th Cir.·
1990-07-24
·cited 14×
Under Illinois quasi-contract law, a plaintiff who performed services that conferred a benefit on a defendant may recover in quantum meruit despite no direct contract with that defendant, where the defendant induced the work and its retention of the benefit is unjust. However, qu
-
524 So. 2d 1015·
Fla.·
1988-05-12
·cited 14×
The Florida Supreme Court held that the definition of "prevailing party" established in C.U. Associates for mechanics' lien disputes under section 713.29 does not extend to construction contracts. A contractor who recovered less at trial than settlement offers made before trial w
-
498 So. 2d 1377·
Fla. 2d DCA·
1986-12-23
·cited 14×
NCN Electric, the prevailing party in a mechanics lien foreclosure action, appeals the trial court's denial of attorney's fees. The appellate court held that under Florida Statute § 713.29, the award of attorney's fees to the prevailing party is mandatory, and the trial court err
-
This case involves a dispute over a construction contract for a shoe store. The appellate court reversed the trial court's decision, finding that the contractor did not provide sufficient evidence for its findings and that the owner was entitled to additional credits for material
-
Bishop Signs sought to foreclose a mechanic's lien against property owners Magee and Mahon. The trial court dismissed the foreclosure complaint for failure to plead furnishing of a contractor's affidavit as required by statute, discharged the lien, and awarded attorney's fees to
-
The court held that the measure of damages for a contractor's breach by abandonment is the difference between the contract price and the reasonable cost to complete the improvement, not just the cost to cure defects in completed work.
-
This case involves the interaction of Florida's Mechanics' Lien Law and Arbitration Code. The court held that when a trial court confirms an arbitration award, it cannot add pre-award interest if the arbitrators expressly denied such interest, even in the context of foreclosing a
-
In this construction lien dispute arising from the Largo Medical Center project, the court addressed claims by three parties seeking payment for materials and services. The decision clarifies the requirements for mechanic's liens and equitable liens under Florida law, and address
-
Dynamic Builders appeals from a judgment awarding damages to property owners for defective construction work, with the owners cross-appealing. The court affirmed the damages award but reversed the denial of attorney's fees to the builder as the prevailing party on its mechanic's
-
363 So. 2d 344·
Fla. 3d DCA·
1978-06-13
·cited 14×
Flagler Center Building Loan Corp. appealed a foreclosure judgment on a $6 million construction loan, challenging the trial court's findings on default and post-judgment orders. The appellate court reversed, finding that Chemical Realty waived the default through its continued fu
-
348 So. 2d 23·
Fla. 4th DCA·
1977-06-17
·cited 14×
The court held that payments made by the owner before recording a notice of commencement and payments made to complete construction without a notice of recommencement were improper, creating a surplus fund from which the lienholder could recover.
-
Monde Investments, the building owner, appealed judgments in two mechanic's lien foreclosure cases brought by contractors Taylor-Made Enterprises and Hardrives. The court reversed both judgments, finding that Taylor improperly used parol evidence to prove contract extras and that
-
534 F.2d 1050·
2d Cir.·
1976-04-26
·cited 14×
The court held that a suit to enforce a discharged mechanics' lien against a surety bond does not interfere with a Chapter X bankruptcy reorganization and therefore the bankruptcy court should modify its stay to allow the suit to proceed against the surety.
-
306 So. 2d 133·
Fla. 2d DCA·
1975-01-08
·cited 14×
Industrial Supply Corporation and Fennell & Associates appeal a foreclosure judgment prioritizing appellees' mortgage over their mechanics' liens. The Florida District Court of Appeal affirmed, holding that the mortgage validly secured future advances under Fla. Stat. § 697.04 an
-
253 So. 2d 878·
Fla. 4th DCA·
1971-10-28
·cited 14×
The court held that the prevailing party in a mechanics' lien action is entitled to attorney fees, regardless of whether they are the plaintiff or defendant.
-
207 So. 2d 726·
Fla. 4th DCA·
1968-02-28
·cited 14×
An architect sought an equitable lien on property owned by defendants after performing architectural services for a club remodeling project. The trial court dismissed the complaint, but the appellate court reversed, holding that the complaint adequately alleged facts supporting a
-
155 So. 2d 627·
Fla. 1st DCA·
1963-07-16
·cited 14×
The Florida District Court of Appeal resolved a mechanic's lien dispute where a materialman sought to recover the full value of materials supplied to a project that was abandoned before completion, when the owner's contract with the contractor was based on conveyance of real prop
-
A contractor must provide a sworn statement to the owner detailing payments to subcontractors and materialmen to perfect a mechanic's lien, and failure to do so bars the lien.
-
63 So. 2d 60·
Fla.·
1953-02-06
·cited 14×
Curtis seeks to avoid mechanic's liens filed by subcontractors and materialmen by arguing that no final payment was due and that the general contractor failed to provide required affidavits without cautionary notices being served. The Florida Supreme Court held that the $1,950 de
-
The court held that the mechanics' and materialmen's liens were superior to the appellant's attachment lien because, under Kentucky law, such statutory liens relate back and take precedence over later-perfected attachment liens, and the attachment lien was not a 'contract lien' o