650 Florida cases classified under this topic, plus 572 listed through its narrower topics · sorted by citation count · see the citation graph · browse and sort
-
The appellate court held that the trial court erred in granting summary judgment because genuine issues of material fact existed regarding the amounts billed, and also erred in denying the motion for leave to amend pleadings.
-
The Thompsons appeal three final judgments in favor of Jared Kane Company, Inc., a lien foreclosure action on their home. The appellate court reversed all three judgments, holding that the trial court abused its discretion by denying the Thompsons' motion to amend their answer an
-
The court held that a mechanic's lien notice served on the 48th day was timely when the 45th day fell on a Saturday and the following Monday was a holiday, and that a quantum meruit claim could be construed as a claim for unjust enrichment.
-
An innocent lienor is entitled to post-seizure interest on its mortgage from the date of seizure until the property is sold, as the government's interest is no greater than that of the wrongdoer.
-
The court held that the district court retained in rem jurisdiction due to the nonparty owner's consent, and that the case must be remanded to determine if the supplier relied on the barge itself, which is a factual question for lien entitlement under the Maritime Lien Act.
-
334 So. 2d 116·
Fla. 3d DCA·
1976-04-27
·cited 21×
The court held that the trial judge did not err in allowing acceleration of the mortgage debt, denying reformation of the default clause, or awarding attorney's fees.
-
529 F.2d 952·
9th Cir.·
1976-01-14
·cited 21×
The Territory of Guam is authorized under section 22 of the Organic Act of 1950 to transfer appellate jurisdiction over local, non-federal cases from the District Court of Guam to a court created by the territorial legislature. The power to create courts and determine the appella
-
The court held that the trial judge abused discretion by awarding an unreasonably low attorney's fee, but did not abuse discretion in denying costs.
-
246 So. 2d 97·
Fla.·
1971-03-31
·cited 21×
The Florida Supreme Court held that when a deadline under the Mechanic's Lien Law falls on Sunday, the deadline is extended to the next business day. The Court declined to require performance of procedural acts on Sunday when the statute is silent on time computation, harmonizing
-
183 So. 2d 237·
Fla. 3d DCA·
1966-01-25
·cited 21×
The court held that the trial court correctly awarded a mechanics lien and partial damages, as both parties contributed to the incomplete performance of the contract.
-
175 So. 2d 88·
Fla. 1st DCA·
1965-05-04
·cited 21×
Massachusetts Bonding & Insurance Company appeals a summary judgment in favor of American Oil Company on a performance bond for unpaid asphalt materials delivered to a road construction contractor. The court affirms, holding that the one-year statute of limitations in Section 255
-
279 F.2d 837·
4th Cir.·
1960-05-31
·cited 21×
A federal tax lien takes priority over a mortgagee's claim for reimbursement of real estate taxes paid after the tax lien was recorded, even though the mortgage was recorded prior to the tax lien, because the mortgagee's lien for such taxes was inchoate and unperfected when the f
-
146 Fla. 247·
Fla.·
1941-02-25
·cited 21×
C.I.T. Corporation, holder of a conditional sales contract on an automobile, appeals a judgment for damages awarded to J.B. Brewer for assault and battery committed by C.I.T.'s repossession agent. The Florida Supreme Court affirmed, holding that an attempt to repossess property i
-
133 So. 553·
Fla.·
1931-04-04
·cited 21×
This case clarifies that a contractor furnishing labor and materials to a married woman's separate property with her knowledge and consent does not need to file a "notice of lien" to enforce payment against her property. The court held that the constitutional provision creating t
-
In this materialman's lien case, the Florida Supreme Court upheld the validity of a lien notice given by a supplier of building materials for work performed on multiple properties owned by the same person, holding that a general notice satisfies statutory requirements and that pr
-
Avatar Development Corporation appealed the denial of attorney's fees after prevailing on a contractual claim for future lost profits in a breach of contract and construction lien case. The court held that where multiple claims in a lawsuit are separate and distinct, the prevaili
-
903 F.2d 114·
2d Cir.·
1990-05-08
·cited 20×
The court held that the district court possessed federal question jurisdiction over Sanders' claim for enforcement of an arbitration award against HUD, and that HUD had waived sovereign immunity. The court also affirmed the district court's decision allowing Sanders to foreclose
-
Plaza Builders contracted to construct a warehouse for Dean Regis but was unable to obtain a contractor's license and instead arranged for a licensed contractor to perform the work. After Regis removed the contractor from the job for defective work, Plaza sued for unpaid contract
-
A contractor who engaged to construct a concrete pad on the owner's property failed to file a required contractor's affidavit before instituting a mechanic's lien foreclosure action. The court held that the affidavit requirement is jurisdictional and cannot be waived, and reverse
-
670 F.2d 1316·
3d Cir.·
1982-01-25
·cited 20×
The filing of a notice of lis pendens under the New Jersey statute does not violate the Fourteenth Amendment's due process guarantee. Although a lis pendens impairs the marketability of property by preventing the owner from conveying clear title, the statute provides adequate pro
-
In a mechanic's lien foreclosure action arising from a home construction dispute, the court determined that the defendant/counterclaimant was the prevailing party entitled to attorney's fees under Florida Statutes § 713.29, despite the contractor recovering a judgment for $3,280.
-
This case addresses whether prejudgment interest should be awarded on claims arising from a water and sewer system construction project. The court affirmed denial of prejudgment interest on the contractor's claim because it was unliquidated due to unresolved subcontractor claims,
-
In this construction contract dispute, the appellate court reversed the trial court's award of attorneys' fees to GDC (the developer) because GDC failed to establish its mechanics' lien claim but obtained a money judgment for labor and materials, making it not a prevailing party
-
A contractor must furnish the affidavit required by Section 713.06(3)(d), Florida Statutes, even if the owner is also the general contractor, unless the contractor can plead and prove compliance or inapplicability.
-
355 So. 2d 217·
Fla. 1st DCA·
1978-02-24
·cited 20×
A subcontractor who performed work on a land-clearing project sought a mechanic's lien and equitable lien against the property owners and a surety bond after the general contractor failed to pay him. The court held that because the subcontractor furnished materials and equipment
-
351 So. 2d 399·
Fla. 2d DCA·
1977-11-04
·cited 20×
McCLain Construction appealed the trial court's order reducing a surety bond securing its mechanic's lien foreclosure claim. The trial court had granted partial summary judgment dismissing one mechanic's lien count and reduced the bond accordingly, but the appellate court reverse
-
A materialman who furnished supplies to a subcontractor sought to foreclose a mechanic's lien against property that had been conveyed to a corporation. The court reversed judgment against the original owners and their surety bond company, holding that the actual property owner (t
-
Imperial Industries and Triangle Properties appealed an order denying their motion to vacate defaults and set aside a default judgment in a mechanic's lien foreclosure action. The Florida appellate court reversed, holding that the trial court erred in failing to apply the liberal
-
318 F.2d 881·
4th Cir.·
1963-05-21
·cited 20×
The federal insolvency statute (31 U.S.C. § 191) grants the United States absolute priority over mechanic's liens when a debtor is insolvent and has committed an act of bankruptcy, overriding state law and the common law 'first in time, first in right' principle. However, this pr
-
98 So. 2d 77·
Fla.·
1957-11-06
·cited 20×
A buyer refused to pay for an installed awning, claiming it was not what he bargained for, but the court found the installation met the contract's specifications for dimensions and type.
-
89 So. 2d 774·
Fla.·
1956-09-12
·cited 20×
All State Pipe Supply seeks to foreclose a mechanic's lien against property owners who paid their contractor in full without obtaining the required sworn statement. The Florida Supreme Court held that a materialman's failure to provide a cautionary notice does not bar enforcement
-
227 F.2d 359·
7th Cir.·
1955-11-18
·cited 20×
A mechanic's lien that is properly recorded before a federal tax lien arises and is recorded takes priority over the federal tax lien under the principle of "first in time, first in right." The federal tax lien created by section 3670 of the Internal Revenue Code does not carry a
-
81 So. 2d 489·
Fla.·
1955-06-17
·cited 20×
Tremont Company appeals a decree foreclosing mechanic's liens on motor cottage property. The court held that where a vendor contract expressly requires a vendee to construct improvements, mechanic's liens attach to both the vendor's and vendee's interests, even though the vendor'
-
62 So. 2d 589·
Fla.·
1953-01-13
·cited 20×
Griffin-Moore Lumber Company held a mechanic's lien on property for materials furnished to construct a building. The United States filed tax liens against the property owner after the mechanic's lien was recorded but before the foreclosure suit was brought. The Florida Supreme Co
-
A hardware company sought to enforce a materialman's lien against a purchaser of property where building materials were supplied. The Florida Supreme Court reversed the lower court's decree, holding that a materialman's lien, though properly recorded within three months, is ineff
-
South Florida Coastal Electric appeals a summary judgment in favor of Treasures on the Bay II Condo Association, arguing the trial court improperly granted summary judgment on an affirmative defense despite material disputes of fact. The court reverses, holding that unresolved fa
-
GCA sought attorney's fees in a construction lien dispute that was arbitrated under the parties' contract. The court reversed the trial court's finding that the parties waived their statutory right to have the circuit court decide attorney's fees by submitting the issue to arbitr
-
660 So. 2d 623·
Fla.·
1995-05-11
·cited 19×
The Florida Supreme Court answered a certified question of great public importance regarding when a subcontractor begins to furnish services for purposes of the mechanic's lien notice requirement under Florida Statute § 713.06(2)(a). The Court held that the 45-day notice period b
-
59 B.R. 340·
S.D. Fla.·
1986-03-20
·cited 19×
The court affirmed the bankruptcy court's orders approving substantive consolidation and confirming the plan of reorganization, finding no reversible error.
-
247 So. 2d 791·
Fla. 3d DCA·
1971-05-18
·cited 19×
Art Berman Concrete appeals the dismissal of its mechanic's lien foreclosure complaint. The court addresses whether F.S. § 713.06(3)(d)1 requires sub-contractors to provide notice of unpaid lienors to the owner as a prerequisite to enforcing a mechanic's lien. The court holds tha
-
117 So. 2d 747·
Fla. 2d DCA·
1960-02-05
·cited 19×
Davis, a professional grove caretaker, performed labor improving a citrus grove owned by Arthur S. Dewing. The court upheld an equitable lien on the property for Davis's unpaid services, finding that Dewing permitted and benefited from the work, though the court reversed the port
-
117 So. 2d 240·
Fla. 2d DCA·
1959-12-30
·cited 19×
Property owners appealed a mechanics' lien judgment awarding funds to a general contractor and subcontractors. The court affirmed awards to the subcontractors (Giffen Industries and Overhead Door Company) but reversed the award to the general contractor, holding that he could not
-
100 Fla. 1191·
Fla.·
1930-11-12
·cited 19×
Stockton Mortgage Company sought to foreclose a mortgage on R.W. Weaver's homestead executed in June 1926, but Weaver died days later in July 1926. The defendants pleaded that no money was ever advanced to Weaver during his lifetime, making the mortgage void for lack of considera
-
Sewell Masonry Company appeals the dismissal of its construction lien and breach of contract action for lack of prosecution under Florida Rule of Civil Procedure 1.420(e). The trial court dismissed the case after finding multiple periods of inactivity exceeding one year, with no
-
VL Orlando Building Corp. sued AGD Hospitality Design & Purchasing, Inc. in Broward County for breach of a construction contract involving Orlando property. When AGD counterclaimed for mechanic's lien foreclosure and moved to transfer venue to Orange County, the trial court grant
-
In this construction dispute, a contractor appealed a trial court judgment awarding net damages to homeowners after the contractor's mechanic's lien foreclosure was defeated by the owners' counterclaim for breach of contract and defective workmanship. The appellate court affirmed
-
445 So. 2d 1136·
Fla. 2d DCA·
1984-03-02
·cited 18×
Contractors Schabert and Crews appealed a judgment awarding them $7,803.90 in breach of contract damages against homeowners Montaltos, challenging the trial court's denial of a mechanics' lien, rejection of extras claims, and award of attorney's fees to the homeowners. The court
-
The court held that the second amended complaint relates back to the date of the first amended complaint, thus the statute of limitations did not bar the action.
-
In this construction contract and mechanic's lien dispute, the trial court ruled in favor of contractor Nezelek against developer Gesco, finding Gesco responsible for construction delays and awarding Nezelek full recovery on a transfer bond. On appeal, the court affirmed the vali
-
392 So. 2d 573·
Fla. 4th DCA·
1980-11-05
·cited 18×
This case concerns whether a stipulation extending the time to respond to a "show cause" order in a mechanics' lien proceeding is valid, or if the statutory 20-day period is mandatory and jurisdictional. The court held that such stipulations are valid and not jurisdictional, mean