A materialman brought a mechanic's lien foreclosure against property owners who were not in privity with the materialman. The owners challenged the validity of the lien and sought to offset damages from a subcontractor's breach of contract. The court affirmed the judgment in favo
-
226 So. 2d 35·
Fla. 1st DCA·
1969-08-14
Trowbridge, Inc., a subcontractor, appealed a judgment denying enforcement of its mechanic's lien against property owners William and Lucille Hathaway. The court affirmed the lower court's ruling that Trowbridge failed to comply with Florida's mechanic's lien statute by failing t
-
The appellate court reversed a lower court's decree enforcing a mechanic's lien, finding that the building was not substantially completed in accordance with the contract. The court remanded the case with instructions to dismiss the complaint.
-
394 F.2d 174·
9th Cir.·
1968-04-29
The court held that the facts and circumstances did not evidence an injustice to the appellant under the rulings of the Referee or the District Court.
-
393 F.2d 187·
7th Cir.·
1968-04-01
The court held that Prepakt was entitled to interest on its mechanics lien claim but not on its contract claim, and that a bond premium was not a covered cost under the labor and material bond.
-
206 So. 2d 655·
Fla. 3d DCA·
1968-02-06
The court affirmed the granting of a default judgment against a defendant who failed to file an answer within the time ordered by the court, despite filing an answer and counterclaim shortly after the default was entered.
-
The court held that the defendant's appeal lacked merit and affirmed the judgment and sentence.
-
A materialman sought to foreclose a mechanic's lien for materials incorporated into a construction project. The court denied the defendant-owner's motion for summary judgment, holding that the failure to serve notice of lien within 45 days does not automatically bar the lien if n
-
203 So. 2d 204·
Fla. 1st DCA·
1967-10-05
National Union Fire Insurance Company appeals summary judgments awarding subcontractors recovery on a performance bond despite the principal's fraud in obtaining the bond. The court holds that fraud by the principal does not vitiate the surety's liability to innocent obligees who
-
The court reviewed a pre-trial order concerning a materialman's lien, where the owners contended that the cost to complete a defaulted construction contract should be deducted from the remaining contract balance before satisfying the lien.
-
377 F.2d 137·
D.C. Cir.·
1966-12-01
The court held that the owners did not owe the general contractor any sums when the subcontractors perfected their liens, thus precluding subcontractor recovery.
-
Russell, Inc. sought to foreclose a mechanic's lien against the Opers for landscaping services provided to their residence. The court upheld the lien despite defendants' challenge that plaintiff failed to provide a sworn statement as required by Florida statute, finding that dire
-
Maule Industries appealed a summary judgment denying its mechanic's lien foreclosure action on the ground that its lis pendens failed to strictly comply with statutory requirements. The Fourth District Court of Appeal reversed, holding that the lis pendens achieved substantial co
-
176 So. 2d 119·
Fla. 2d DCA·
1965-05-28
Frank, as trustee and owner of land, appeals a final decree granting an equitable lien to engineering plaintiffs who performed subdivision services benefiting his property through an option holder corporation in which he held a financial interest. The court affirms, holding that
-
172 So. 2d 849·
Fla. 2d DCA·
1965-03-17
A mechanics' lien case involving whether a sewerage treatment system's equipment can be subject to a mechanic's lien when the contractor had no interest in the underlying land. The court held that the equipment is removable under Florida law and remanded for the trial court to im
-
172 So. 2d 508·
Fla. 2d DCA·
1965-02-24
Central Electric Supply, an unpaid materialman, appealed a summary judgment denying its mechanics' lien claim against a general contractor for materials supplied to a subcontractor in June-September 1961. The court affirmed, holding that because visible commencement of operations
-
The court held that the attorney had authority to execute releases and that the releases did not contravene public policy, were supported by consideration, and the pre-trial order was properly modified.
-
333 F.2d 1005·
9th Cir.·
1964-06-16
The court held that a taxpayer can only deduct a theft loss for amounts paid in reliance on a contractor's false representation that subcontractors and materialmen were being paid, not for defective workmanship not shown to be knowingly and designedly caused.
-
158 So. 2d 142·
Fla. 2d DCA·
1963-11-27
In this equity case, the trial court dismissed plaintiff's third amended complaint for failing to allege a cause of action in equity and transferred the case to the law side with leave to file an amended complaint. The defendants appealed the transfer, arguing the plaintiff canno
-
324 F.2d 892·
D.C. Cir.·
1963-11-14
The court held that the trial court's findings of fact were supported by evidence and not clearly erroneous, thus upholding the judgment.
-
316 F.2d 812·
5th Cir.·
1963-05-08
A party in possession of land under a contract to purchase is not considered an 'owner' for the purpose of impressing a mechanic's lien. A settlement payment from the landowner to the trustee was for 'peace' and not a purchase of the bankrupt's interest.
-
Appellants appealed from a foreclosure decree on a mechanic's lien for swimming pool and patio construction work. The trial judge awarded the contractor $3,800, finding the work was substantially performed but required approximately $700 in repairs to complete properly.
-
310 F.2d 857·
D.C. Cir.·
1962-11-01
The court held that the trial court's findings were not clearly erroneous and affirmed the judgment.
-
305 F.2d 332·
7th Cir.·
1962-07-10
The court modified its prior order, affirming the priority of mechanic's liens over the United States' lien, and reversing the priority of the United States' lien over Crest Finance's lien.
-
In this materialman's lien foreclosure dispute, the Florida appellate court reversed a summary decree that had granted the lienholder priority over a bank's mortgage. The court determined that genuine issues of material fact existed regarding whether materials were furnished as p
-
19 Fla. Supp. 11·
Dade Cty. Cir. Ct.·
1961-11-28
Materials are considered 'specially fabricated' for a mechanic's lien only if they have little value if not used for the particular improvement.
-
131 So. 2d 513·
Fla. 2d DCA·
1961-06-30
The appellate court affirmed a final decree foreclosing mechanics' liens filed by subcontractors and an engineering company against owners who had contracted with a general contractor who subsequently absconded.
-
128 So. 2d 172·
Fla. 2d DCA·
1961-03-29
The Florida District Court of Appeal reversed a lower court's decision that granted a mechanic's lien to a plaintiff who had purchased a note and mortgage. The appellate court found that the contractor was not entitled to a mechanic's lien and therefore could not assign one to th
-
The court held that the parties are bound by their agreement to conduct arbitration under the American Arbitration Association rules, which do not require detailed findings of fact or conclusions of law for an award to be entered as a judgment.
-
278 F.2d 488·
6th Cir.·
1960-05-11
The court held that a trade fixture, not permanently attached to leased premises, is not subject to a mechanic's lien under Kentucky law.
-
118 So. 2d 38·
Fla. 2d DCA·
1960-02-19
Property owners appealed a summary judgment holding them liable for the full difference between contract price and down payment to satisfy mechanic liens. The court reversed, holding that 'final payment' for mechanic lien purposes must be determined by what the parties actually s
-
The court held that parol evidence was inadmissible to explain a written waiver of lien, and the refusal to transfer the case to the law side was proper because a complete defense to the lien was proven.
-
The court held that the defendant was liable for the full amount of the mechanic's and materialmen's liens because he breached the indemnity contract, and the benefits of settlements with lien claimants did not accrue to the plaintiff.
-
108 So. 2d 486·
Fla. 3d DCA·
1959-01-29
M. & M. Electric Co. sued Diana Stores and general contractor R. M. Thompson Co. for unpaid electrical work. The trial court awarded M. & M. $3,729 and dismissed Thompson's counterclaim for breach of contract and poor scheduling. The appellate court reversed, finding M. & M. was
-
231 F.2d 761·
D.C. Cir.·
1956-02-16
The court held that a party cannot unilaterally withdraw from an arbitration agreement that has become a stipulation of the court, especially after significant reliance and expenditure by the other party.
-
224 F.2d 177·
10th Cir.·
1955-06-29
Improvements on land held in trust by the United States for an Indian ward are not subject to state mechanics' lien laws and cannot be sold to satisfy such liens.
-
219 F.2d 509·
D.C. Cir.·
1955-02-08
The court held that the subcontractor, having voluntarily released its lien in exchange for a postdated check, became an unsecured general creditor and could not establish a constructive trust against the bankrupt estate.
-
The Florida Supreme Court affirmed a lower court's decision voiding a note and mortgage due to usury. The court found that the lender willfully and knowingly charged excessive interest, forfeiting the entire principal and interest as per state statute.
-
65 So. 2d 32·
Fla.·
1953-05-08
In this mechanics' lien case, the Florida Supreme Court reversed a motion to dismiss and held that a contractor who performed demolition and salvage work on property owned as an estate by the entireties could establish a valid mechanics' lien without providing notice to the non-o
-
A materialman's lien is valid against multiple houses in a single project even if specific materials cannot be traced to each house, provided the project was treated as an entirety by the parties.
-
A plaintiff is entitled to amend a mechanic's lien foreclosure bill to allege compliance with statutory notice requirements, even after testimony has been taken, if the amendment concerns a procedural right and no inequity results.
-
1 Fla. Supp. 20·
Dade Cty. Cir. Ct.·
1951-05-29
A defendant waives a challenge to personal jurisdiction by pleading and going to trial on the merits after the challenge is denied. A contractor's sworn statement is not a condition precedent to acquiring a lien, but rather protects the owner from double payment.
-
175 F.2d 890·
8th Cir.·
1949-07-21
The court held that the lessor waived her right to assert a secured claim for improvements made by the tenant, as she failed to utilize available protections and waived strict performance of the lease covenants.
-
173 F.2d 882·
6th Cir.·
1949-04-11
The court held that Tennessee mechanics' and furnishers' lien statutes do not grant a lien on machinery owned by a lessee and temporarily placed on leased property, especially when the leasehold is not for a term of years. The court also affirmed the disallowance of overtime char
-
The court held that the appellee, having purchased the property for value without notice, is a bona fide purchaser, and the appellants' claims are barred by their delay and failure to act.
-
A mechanic's lien that was properly filed under the Texas statute, for work intended to make a building a permanent fixture, is superior to a deed of trust that arose later in time.
-
152 F.2d 678·
D.C. Cir.·
1945-12-24
The court held that the sureties were liable for losses caused by the principal's failure to complete construction and discharge liens within the bond periods, and that the trial court properly instructed the jury on damages and rejected certain defenses.
-
142 F.2d 102·
D.C. Cir.·
1944-04-28
The court held that advance payments made by owners to a general contractor do not defeat subcontractors' liens unless the owners acted in bad faith to avoid those liens.
-
143 Fla. 629·
Fla.·
1940-07-05
Cama Mortgage Company sought to foreclose a construction mortgage on property owned by Elizabeth Brachten. The defendant contractor L. H. Connelly counterclaimed for a mechanic's and laborer's lien. The trial court struck Connelly's amended answer and counterclaim, and the Florid
-
143 Fla. 222·
Fla.·
1940-05-24
This case involves a dispute over a construction contract between Augusta E. Thoma and Gustav Weber/Modern Manors, Inc. for building a home in Miami, Florida. The central issue is whether Thoma agreed to a fixed-price contract of $9,840 for construction, fills, and landscaping, o