650 Florida cases classified under this topic, plus 572 listed through its narrower topics · sorted by citation count · see the citation graph · browse and sort
-
The Florida Supreme Court held that a contractor's failure to deliver a required affidavit before filing a mechanic's lien foreclosure action is not a jurisdictional defect, but rather a condition precedent that can be cured by amended complaint if the statute of limitations has
-
First Atlantic Building Corporation appeals a judgment awarding Neubauer Construction Company $37,774 for breach of a construction contract. The court affirmed liability but reversed the damages calculation and remanded for retrial on the damages amount, entitlement to materials
-
This case concerns the effect of a reversed foreclosure decree on a sale that occurred during the appeal. The court held that a complete reversal of a foreclosure decree vacates any sale conducted under that decree, requiring a resale and an accounting for rents and profits.
-
886 F.2d 986·
8th Cir.·
1989-09-14
·cited 38×
The court held that the evidence was sufficient to establish a pattern of racketeering activity under RICO, and that the alleged enterprise was distinct from the persons involved.
-
Babe's Plumbing, a subcontractor, sued property owners to foreclose a mechanic's lien under Florida law but failed to provide the statutory sworn statement required by the Mechanic's Lien Law. The court affirmed summary judgment against the subcontractor, holding that strict comp
-
Standard Accident Insurance Co., as surety on a contractor's bond, sought reversal of a decree requiring it to indemnify the owner Sullivan for materialman's liens on construction work. The Florida Supreme Court reversed, holding that when an owner receives statutory notice of a
-
542 So. 2d 957·
Fla.·
1989-03-16
·cited 37×
The Florida Supreme Court held that a subcontractor on a public works project cannot lawfully waive its rights to a contractor's payment and performance bond required by statute, even if the subcontract contains explicit waiver language. The court found such waivers violate publi
-
503 So. 2d 1232·
Fla.·
1986-12-24
·cited 37×
Florida Steel Corporation sought to recover unpaid materials supplied to a construction project abandoned by the primary contractor. The Florida Supreme Court held that the Alton Towers rule limiting owner liability does not apply when a project is abandoned for an extended perio
-
The court held that Texas law does not preclude recovery on a separate labor and material bond even when a Hardeman Act bond has been posted, and that the work performed by the plaintiff was sufficient to toll the notice period under the bond.
-
84 Fla. 662·
Fla.·
1922-12-12
·cited 37×
This case concerns the priority of liens between a mortgage holder and materialmen/laborers in a construction project. The court clarified that mechanic's liens attach individually and are prioritized based on when the materials were supplied or labor performed, not from the proj
-
The D'Oench, Duhme doctrine and its statutory codification, 12 U.S.C. § 1823(e), preclude a party from asserting claims based on agreements not properly executed by the financial institution, even if written and in the bank's records, to protect federal receivers like FSLIC from
-
Gerald Falovitch appealed a judgment foreclosing a mechanic's lien filed by Gunn and Gunn Construction Company. The court reversed because the contractor failed to comply with the statutory requirement of serving an affidavit to the owner at least five days before instituting sui
-
80 Fla. 679·
Fla.·
1920-11-11
·cited 36×
The Florida Supreme Court reversed a lower court decree that sought to subject Mary Bell Agin's separate property to a material supplier's claim for lumber and materials furnished to a contractor building a house on her land. The court held that without privity of contract and th
-
The trial court erred by denying appellant the opportunity for oral argument after announcing parties could submit memoranda and summaries, and by admitting evidence of oral change orders when the contract required written ones, potentially allowing modification by conduct.
-
-
Beach Resorts International appeals the trial court's award of attorney fees to Clarmac Marine in a mechanic's lien foreclosure action that was resolved through binding arbitration. The court reverses, holding that when a dispute is resolved through arbitration and the defendant
-
In this interlocutory appeal from a mechanic's lien foreclosure action, the Fourth District Court of Appeal affirmed the trial court's denial of the defendant's motion to dismiss for lack of jurisdiction and alternative motion to compel arbitration. The court held that while an a
-
473 F.2d 1210·
2d Cir.·
1973-02-01
·cited 34×
The Federal Reserve Board did not exceed its authority in promulgating a regulation that includes statutory liens within the definition of 'security interest' for the purpose of the Truth-in-Lending Act's rescission provision.
-
262 So. 2d 671·
Fla.·
1972-05-03
·cited 34×
The Florida Supreme Court held that when a contractor defaults on a direct contract with a property owner, the owner may offset the reasonable costs of completing the work against the unpaid balance of the contract price before a materialman (supplier) can claim a lien against th
-
The court held that a default judgment imposing personal liability on a non-contracting spouse for breach of contract, when the complaint only sought foreclosure of a construction lien against their property interest, is void and must be vacated.
-
412 So. 2d 883·
Fla. 2d DCA·
1982-03-17
·cited 33×
Arrow Air Conditioning sued Coffee Pot Plaza Partnership for unjust enrichment after performing refrigeration equipment repairs for Gulf Shores Industries, which leased part of Coffee Pot's shopping center. The court reversed the trial court's unjust enrichment judgment against C
-
644 F.2d 1097·
5th Cir.·
1981-05-14
·cited 33×
The court held that the district court did not err in its jury instructions regarding negligence, prevention of performance, or substantial performance, nor in excluding the Goldsmith Report as inadmissible settlement evidence. However, the court reversed and remanded the portion
-
356 So. 2d 925·
Fla. 2d DCA·
1978-03-29
·cited 33×
The court held that while the trial court erred in requiring proof of actual malice for a slander of title claim, this error was harmless because the plaintiff failed to prove special damages. The court affirmed the award for the defendant on its counterclaim.
-
MacIntyre, a homeowner, appealed a judgment for his architect Ramos on both a negligence claim and a counterclaim for additional architectural fees. The court affirmed the judgment dismissing the negligence claim but reversed the judgment awarding Ramos additional fees, holding t
-
61 So. 2d 634·
Fla.·
1952-11-21
·cited 33×
This case examines the requirements for materialmen and subcontractors to enforce liens against property owners under Florida's Mechanics' Lien Law. The Supreme Court of Florida clarified that a materialman without privity of contract with the owner must strictly comply with stat
-
6 So. 2d 818·
Fla.·
1942-03-06
·cited 33×
This case concerns whether a contractor who performed renovations based on a sub-lease agreement can claim a mechanic's lien against the property owner and original lessee. The court found that the contractor failed to establish a direct contract or sufficient statutory notice to
-
Bruce Construction Corporation appealed the dismissal of its lien enforcement action, claiming its mechanic's lien should take priority over L.M. Adams' mortgage. The Florida Supreme Court held that a conditional lien release was effective only to the extent of the $20,000 consid
-
49 Fla. 347·
Fla.·
1905-01-01
·cited 33×
Ocala Foundry appeals a chancery decree denying its claim for a mechanic's lien on machinery repaired for the Ocklawaha Lumber Company. The Florida Supreme Court reverses, holding that retention of possession beyond three months does not extinguish a mechanic's lien and does not
-
39 Fla. 218·
Fla.·
1897-01-01
·cited 33×
J. H. Boden sought to enforce a mechanic's lien against church trustees and others for unpaid work on a church building. The lower court entered a decree pro confesso against the defaulting defendants and awarded attorney fees, but the Florida Supreme Court reversed the attorney
-
423 So. 2d 500·
Fla. 3d DCA·
1982-12-14
·cited 32×
Peninsular Supply Company, a materialman not in privity with the property owner, sought to impose an equitable lien on undisbursed construction funds after failing to perfect a statutory mechanics' lien due to an untimely notice to the owner. The court reversed the trial court's
-
A mechanic's lien foreclosure plaintiff voluntarily dismissed its action and immediately refiled against the same defendant. The trial court denied the defendant's motion for attorney's fees and costs, deferring the award pending the new action's outcome. The court reversed, hold
-
237 So. 2d 330·
Fla. 4th DCA·
1970-06-29
·cited 32×
The Fourth District Court of Appeal reversed a summary judgment for a mechanic's lien, holding that while the contractor had a right to lien the lessors' fee interest in the property, there remained a material factual question about whether the contractor had a duty to mitigate d
-
851 F.2d 1321·
11th Cir.·
1988-08-10
·cited 31×
Private defendants may assert a qualified immunity defense in § 1983 actions when they act in good faith reliance on state law that was not clearly unconstitutional at the time of their conduct. P&M is entitled to qualified immunity because, although the Alabama attachment proced
-
The court held that the assignee's action to enforce a mechanic's lien against a property owner was a matter of state law, not federal law, and thus the district court lacked subject matter jurisdiction.
-
In this cross-appeal involving an architect's contract dispute, the Florida Fourth District Court of Appeal addressed whether filing a mechanic's lien action changes a party's rights under an arbitration agreement, and what costs and interest can be added to an arbitration award
-
369 So. 2d 591·
Fla. 1st DCA·
1978-07-12
·cited 30×
Snead Construction appealed a judgment awarding Avanti Construction $67,603.26 for incomplete subcontract work on two hotels, along with prejudgment interest and attorney's fees. The court affirmed the judgment and interest award but reversed the attorney's fees award, holding th
-
63 So. 2d 264·
Fla.·
1953-02-06
·cited 30×
The Florida Supreme Court held that an owner's final payment to a general contractor is not 'properly made' under Florida's Mechanics' Lien Law unless the owner first secures a sworn statement from the contractor listing all subcontractors and materialmen with their amounts due.
-
152 Fla. 781·
Fla.·
1942-12-18
·cited 29×
Fred Howland, Inc. contracted to complete construction on a Fort Lauderdale hotel building for $29,000 on the exterior work and $125,500 for completion. When Howland's lien foreclosure failed due to non-compliance with statutory requirements regarding sworn statements of subcontr
-
100 Fla. 456·
Fla.·
1930-09-03
·cited 29×
The court reversed the chancellor's decree, holding that the mortgage lien of the Tampa Stock Farms Dairy Company was superior to the materialman's lien of the Armstrong Cork and Insulation Company. The court reasoned that the mortgage was not a legal mortgage until the corporate
-
A party waives its contractual right to arbitration by filing a compulsory counterclaim and initiating discovery before the court rules on a motion to dismiss based on the arbitration clause.
-
Encompass Incorporated appealed the trial court's denial of its motion for attorney's fees and pre-judgment interest following acceptance of a settlement offer under Rule 1.442. The court held that Encompass was not entitled to attorney's fees under Section 713.29 because it did
-
400 So. 2d 1245·
Fla. 5th DCA·
1981-06-10
·cited 28×
The court held that a mechanics' lienor suing on a payment bond cannot recover attorney's fees exceeding 12.5% of recovery due to the application of section 627.756, Florida Statutes.
-
This case involves a complex construction dispute concerning Mayfair House Condominium where the general contractor (Passalacqua) and developer (Resnick) had disputes over payment and construction defects. The court affirmed the trial judgment for Mayfair against Resnick and Pass
-
305 So. 2d 777·
Fla.·
1974-10-30
·cited 28×
Florida Supreme Court discharged a conflict certiorari petition after determining no actual conflict of decisions existed regarding mechanic's lien affidavit requirements for architects and contractors.
-
River Hills, Inc. appealed a judgment foreclosing on a mortgage that contained allegedly usurious interest charges. The appellate court reversed and remanded, holding that the trial court erred in its analysis of the foreign exchange charge and improperly shifted the burden of pr
-
139 So. 2d 159·
Fla. 1st DCA·
1962-03-27
·cited 28×
A contractor who abandons a contract due to their own fault or without sufficient excuse forfeits the right to a mechanics' lien.
-
111 So. 2d 707·
Fla. 3d DCA·
1959-05-05
·cited 28×
Tom Joyce Realty Corp. appeals a mechanic's lien foreclosure brought by contractor H. Popkin & Son for improvements made to leased premises. The court reversed the foreclosure, holding that a contractor cannot obtain a lien against a lessor's interest merely by performing work fo
-
23 Fla. 508·
Fla.·
1887-06-01
·cited 28×
McCarthy appealed a judgment awarding Havis & Perry $11.32 plus costs and attorney's fees for work and materials furnished in constructing buildings on his property. The Florida Supreme Court held that an 1885 mechanics' lien statute did not apply retrospectively to work performe
-
18 Fla. 809·
Fla.·
1882-01-01
·cited 28×
In this 1882 Florida Supreme Court case, materialmen Doig & Geiger sought to charge real property with a lien for lumber used in constructing a house, claiming Thrasher had promised payment. The court reversed the decree because Thrasher held title as trustee for his wife and chi
-
A homeowner appeals the denial of her motion to vacate a summary judgment for unjust enrichment entered against her in a contractor dispute. The court reversed, holding that the trial court abused its discretion by awarding unliquidated damages without providing the defaulting ho