650 Florida cases classified under this topic, plus 572 listed through its narrower topics · sorted by citation count · see the citation graph · browse and sort
-
This case involves a mechanic's lien foreclosure action where a roofing contractor (Peninsular) sued to recover payment for roof repair work, and the homeowner (Reitano) counterclaimed for breach of contract and negligent construction after water damage occurred while her house w
-
446 F.2d 439·
2d Cir.·
1971-07-01
·cited 8×
A subcontractor suing a surety on a payment bond may recover in quantum meruit the fair and reasonable value of its work and materials to the obligee, and the trial court's valuation was supported by the evidence and was not clearly erroneous. The surety and joint venture were no
-
243 So. 2d 438·
Fla. 3d DCA·
1971-01-26
·cited 8×
-
238 So. 2d 606·
Fla.·
1970-07-01
·cited 8×
Stanley Builders sought to foreclose a mechanics' lien for unpaid construction work, but the trial court dismissed the action, finding that Stanley Builders had split its cause of action by asserting a cross-claim in a separate Civil Court action. The Florida Supreme Court revers
-
The court held that the district court erred in dismissing the case for lack of jurisdiction based on the amount in controversy, as the good faith allegation of the jurisdictional amount should not be dismissed unless recovery is legally certain to be less than the required amoun
-
Imperial Towers appeals the denial of its motion to vacate a default decree in a lien foreclosure suit. The court reverses, finding that improper service of process combined with excusable neglect entitled the defendant to relief and an opportunity to defend on the merits.
-
369 F.2d 551·
9th Cir.·
1966-12-01
·cited 8×
The court held that the bankruptcy court had summary jurisdiction to determine the validity of a mechanics lien against property in its constructive possession, but erred in restraining the lienholder from pursuing a separate action against a third party.
-
192 So. 2d 15·
Fla. 1st DCA·
1966-11-15
·cited 8×
A contractor must comply with statutory requirements, including providing an affidavit and recording a claim of lien, to maintain an action to foreclose a mechanic's lien.
-
362 F.2d 486·
4th Cir.·
1966-06-01
·cited 8×
A surety cannot use subrogation to offset losses on one construction contract against excess funds realized on a separate contract, even if both contracts were with the same contractor and surety.
-
164 So. 2d 560·
Fla. 3d DCA·
1964-06-02
·cited 8×
Roy Loving appealed the dismissal of his mechanics' lien foreclosure complaint. The trial court dismissed for failure to state a cause of action, lack of jurisdiction over parties, and lack of subject matter jurisdiction. The appellate court affirmed the dismissal on the pleading
-
324 F.2d 77·
9th Cir.·
1963-10-24
·cited 8×
The court held that a secured creditor does not necessarily lose its lien by failing to file a secured claim within six months if the bankruptcy court orders that the validity and priority of liens will be determined later. The court also held that the trustee's order to sell pro
-
148 So. 2d 569·
Fla. 1st DCA·
1963-01-17
·cited 8×
Failure to file a notice of pendency within one year of filing a claim of lien bars the foreclosure action, but does not abate an action for the debt itself.
-
145 So. 2d 505·
Fla. 2d DCA·
1962-09-26
·cited 8×
In this interlocutory appeal, the court addresses whether a defendant compelled to file a legal counterclaim in an equity suit has an absolute right to a jury trial on that counterclaim. The court held that while a defendant normally has a constitutional right to jury trial on le
-
142 So. 2d 786·
Fla. 1st DCA·
1962-07-05
·cited 8×
Failure to file a notice of pendency of action within one year of filing a mechanic's lien claim discharges the lien against the property, even if the owner had actual notice.
-
128 So. 2d 623·
Fla. 3d DCA·
1961-03-20
·cited 8×
The court reversed the chancellor's determination that Troup Bros., Inc. held a valid mechanic's lien for road construction work, holding that Troup Bros. was a contractor rather than a mere materialman and therefore was required to provide the sworn statement mandated by Florida
-
A defendant waives the defense of lack of personal jurisdiction if they fail to raise it timely, particularly after filing an answer and counterclaim on the merits.
-
276 F.2d 190·
2d Cir.·
1960-03-23
·cited 8×
The court held that the dismissal of the Chapter X reorganization petition was proper because there was no reasonable expectation of a successful reorganization plan.
-
Payments received by a creditor from a bankrupt are not preferential if, at the time of payment, the creditor could have secured the debt by filing a valid lien that would not have improved their position relative to other creditors.
-
80 So. 2d 351·
Fla.·
1955-05-11
·cited 8×
The Florida Supreme Court affirmed a lower court's decision, holding that a conveyance of property was not fraudulent and that the appellant was not entitled to an equitable lien for labor and materials furnished because they failed to foreclose on their mechanic's lien within th
-
129 F.2d 314·
6th Cir.·
1942-06-01
·cited 8×
The court held that asserting a perfected mechanic's lien claim in bankruptcy court within the statutory enforcement period is equivalent to bringing an action in state court, thus preserving the lien.
-
145 Fla. 216·
Fla.·
1940-12-03
·cited 8×
This case clarifies the liability of landowners under Florida's 1935 Mechanics' Lien Law. The court held that landowners are liable to laborers for unpaid wages, even without written notice, if they fail to ensure laborers are paid or withhold sufficient funds from contractors.
-
Rieck & Fleece, Inc. sought to enforce a materialman's lien against property owners for building materials supplied in 1935. The Florida Supreme Court affirmed dismissal of the complaint because the suit was filed more than twelve months after furnishing the materials without a s
-
Kennard, an architect and engineer, sued the State Tuberculosis Board for unpaid professional services rendered during construction of a state building. The Florida Supreme Court affirmed the dismissal, holding that Section 9 of Chapter 12284 (Acts of 1927), which purported to au
-
The Florida Supreme Court reversed a lower court order that overruled a demurrer to an amended complaint seeking to subject a married woman's separate property to a lien for improvements. The court held that the notice of lien failed to comply with statutory requirements by not i
-
98 Fla. 683·
Fla.·
1929-10-17
·cited 8×
This case involves a dispute over the priority of liens between a construction lender and a mechanic's lien holder. The court determined that a mortgage securing a building loan, even if funds are disbursed in installments, takes priority from its recording date over subsequently
-
59 Fla. 479·
Fla.·
1910-01-01
·cited 8×
The Florida Supreme Court reversed a decree enforcing a mechanic's lien against the DeSoto National Bank, holding that the lien claimant failed to substantially comply with statutory notice requirements. The Court found that the notice served did not meet the statutory standard f
-
45 So. 3d 887·
Fla. 3d DCA·
2010-09-15
·cited 7×
Commercial Jet sought to foreclose a mechanic's lien on a Boeing 767 aircraft for unpaid maintenance services. The court affirmed summary judgment for U.S. Bank, holding that a mechanic's lien under Florida Statute § 713.58 is possessory in nature and is lost when the lienholder
-
877 So. 2d 34·
Fla. 1st DCA·
2004-06-03
·cited 7×
14th & Heinberg challenged three final judgments enforcing mechanics' liens against its leasehold interest for improvements made by Montgomery Ward. The Florida appellate court held that while a recorded short-form lease must contain an express lien disclaimer to protect a lessor
-
840 So. 2d 316·
Fla. 4th DCA·
2003-02-12
·cited 7×
Palm Coast Builders filed a mechanic's lien against the Levins for unpaid construction costs, but the trial court found the lien fraudulent because it included nonlienable items like pool upkeep, lawn maintenance, HOA fees, and utilities. The Fourth District affirmed, rejecting P
-
646 So. 2d 838·
Fla. 1st DCA·
1994-12-15
·cited 7×
In this mechanic's lien case, Shipwatch Development Corporation appealed a trial court judgment imposing a $16,024.07 lien on its property in favor of contractor Harold Salmon. The appellate court affirmed most of the trial court's factual findings but reversed the attorney's fee
-
Blackton, Inc. appealed a circuit court's dismissal of its construction lien foreclosure action for lack of subject matter jurisdiction. The court held that construction lien foreclosure actions are equitable in nature and fall within county court jurisdiction when the amount in
-
The court held that a party is considered the prevailing party entitled to attorney's fees and costs if they file a complaint to foreclose a construction lien before the opposing party tenders payment.
-
Mirror and Shower Door Products sought to foreclose a construction lien against the Jennings and Seabridge, Inc. The trial court dismissed the complaint for failing to comply with Florida's statutory notice-to-owner requirements. The appellate court affirmed the dismissal against
-
An owner who defeats a mechanics' lien claim is not the prevailing party under section 713.29, Florida Statutes, and therefore cannot recover statutory attorney's fees, when in the same suit the contractor recovers judgment on a related claim for money damages. The prevailing par
-
922 F.2d 895·
1st Cir.·
1990-12-28
·cited 7×
The court held that the bankruptcy court's approval of a settlement agreement, which included the trustee releasing all claims against certain parties, was res judicata and barred appellants from later asserting equitable subordination claims, as they were in privity with the tru
-
Design Aluminum appealed a trial court's dismissal of its mechanic's lien foreclosure action against homeowners, claiming the court erroneously placed the burden on the lienholder to prove a Notice of Commencement was filed. The appellate court reversed, holding that the burden t
-
A Florida appellate court affirmed a mechanic's lien foreclosure judgment but reversed course on prejudgment interest, holding that a subcontractor is entitled to prejudgment interest against a landowner and surety despite lack of privity, in light of the Florida Supreme Court's
-
481 So. 2d 511·
Fla. 1st DCA·
1985-12-30
·cited 7×
Insurance Company of North America appeals a summary judgment in favor of Julien P. Benjamin Equipment Co. for unpaid invoices for materials, equipment, and supplies provided to Hancock Marine on a construction project. The court affirmed the summary judgment, holding that the pl
-
Repair costs for a leased crane damaged by a subcontractor's negligence are not covered by a performance and payment bond that includes 'repairs on machinery'.
-
The Schonfelds sought certiorari review of a trial court order requiring them to increase a mechanic's lien bond to cover the anticipated attorney's fees of their opponent, Hughes Supply, Inc. The appellate court held that Florida's mechanic's lien statute does not authorize tria
-
343 So. 2d 923·
Fla. 3d DCA·
1977-03-15
·cited 7×
A subcontractor appealed a summary judgment dismissing its mechanic's lien foreclosure action, challenging whether preliminary notice mailed to the property owners at their attorney's address (as listed on their recorded deed) was effective service. The court reversed, holding th
-
305 So. 2d 840·
Fla. 3d DCA·
1974-12-31
·cited 7×
Nelson's, Inc. appealed a trial court judgment awarding damages for breach of a construction contract and attorney's fees. The Third District Court of Appeal affirmed the damages award but reversed the attorney's fees award, holding that attorney's fees under Florida's lien statu
-
-
266 So. 2d 355·
Fla. 3d DCA·
1972-09-12
·cited 7×
Warshaw, an engineer, sought a mechanics' lien for professional services rendered in connection with real property owned by the Pymses. The central issue was whether Warshaw had a "direct contract" with the owners under Florida's mechanics' lien statute, where the contract was al
-
193 So. 2d 440·
Fla. 2d DCA·
1967-01-04
·cited 7×
J. P. Driver Company, a sub-subcontractor, appealed the dismissal of its mechanic's lien foreclosure action against property owners and contractors. The court affirmed dismissal, holding that sub-subcontractors lack statutory rights to assert mechanic's liens under Florida law, a
-
A subcontractor sued a prime contractor for payment under a mechanic's lien for extra work performed in making design changes to a shopping center construction project. The trial court awarded the subcontractor the claimed amount, finding the changes were directed by the contract
-
This case concerns a dispute over mortgage priority when an initial mortgage had a description error, and a subsequent mortgage was assigned to a bona fide purchaser. The court had to determine if the assignee of the second mortgage, who had no notice of the error, was protected
-
This case involves a dispute over priority between a mortgage assignee and the owner of the fee, who claimed under a mechanic's lien foreclosure. The court affirmed the lower court's ruling that the mechanic's lien accrued prior to the mortgage, denying foreclosure of the mortgag
-
The Florida Supreme Court affirmed in part and reversed in part a lower court's decree concerning a mechanic's lien foreclosure. The court upheld the personal decree against the principal but reversed the decree against the sureties on the release bond.
-
96 Fla. 683·
Fla.·
1928-12-05
·cited 7×
Contractors who constructed a building sought to enforce a mechanic's lien against the property owners and mortgage holders. The trial court found the contractors had a valid lien but subordinate to prior mortgage liens and material suppliers' liens, and the Florida Supreme Court