384 So. 2d 718·
Fla. 2d DCA·
1980-06-04
·cited 2×
James and Patricia Willis appealed an interlocutory order requiring them to disburse 60% of funds in dispute to Hillsborough Homes, Inc. in a mechanic's lien foreclosure case. The appellate court reversed, finding no evidentiary basis or legal authority for the trial court to ord
-
382 So. 2d 1233·
Fla. 2d DCA·
1980-03-21
·cited 2×
Beaver Industries, a subcontractor, appealed dismissal of its complaint against Westlake Development Corporation for payment under an indemnity contract. The key issue was whether recording a mechanic's lien constitutes "legal action" that would trigger a condition in the indemni
-
372 So. 2d 212·
Fla. 3d DCA·
1979-06-26
·cited 2×
In a mechanic's lien foreclosure action, the trial court struck the property owners' affirmative defense of "no funds" and entered summary judgment for the lienor. The Third District affirmed, holding that the owners' failure to protect themselves under the mechanic's lien statut
-
590 F.2d 207·
6th Cir.·
1979-01-19
·cited 2×
A lien foreclosure action is not an ancillary remedy for judgment collection under Rule 64, nor did the district judge abuse discretion in refusing pendent jurisdiction.
-
365 So. 2d 447·
Fla. 4th DCA·
1978-12-20
·cited 2×
-
First National Commerce and Finance Company purchased an aircraft at a mechanic's lien sale without notifying Indiana National Bank, which held a federally recorded security interest in the aircraft. The court held that while the mechanic's lien sale is valid and the purchaser ta
-
347 So. 2d 830·
Fla. 3d DCA·
1977-07-06
·cited 2×
In this mechanic's lien dispute, the Florida Third District Court of Appeal affirmed the trial court's denial of defendants' motion to dismiss a complaint by a terrazzo installer. The court held that the 45-day notice requirement for mechanic's liens does not bar claims filed aft
-
346 So. 2d 127·
Fla. 1st DCA·
1977-05-25
·cited 2×
Cross State Development and related entities appealed a mechanic's lien foreclosure judgment, arguing that the lien claimant's filing was untimely under Florida law. The court reversed, holding that the lien was filed more than 90 days after the final furnishing of labor or servi
-
345 So. 2d 783·
Fla. 4th DCA·
1977-04-15
·cited 2×
Riviera Beach Partnership appealed a summary judgment foreclosing a mechanic's lien on its property. The court reversed, holding that a property owner may transfer a mechanic's lien to a surety bond after suit is filed, not just before, pursuant to Florida Statute § 713.24.
-
343 So. 2d 646·
Fla. 3d DCA·
1977-03-01
·cited 2×
The court held that oral testimony can be sufficient to prove compliance with statutory lien filing requirements, and that findings based on conflicting testimony will not be reversed.
-
341 So. 2d 259·
Fla. 3d DCA·
1977-01-04
·cited 2×
Planas & Franyie Engineers appealed an award of attorney's fees to the Padillas, arguing it was excessive. The trial court initially awarded $4,000, which this court remanded for reconsideration as excessive. On remand, the trial court awarded $3,500 in attorney's fees for servic
-
In this mortgage foreclosure appeal, the court reversed a summary judgment for the bank because genuine disputes of fact remained regarding whether the contractor's mechanic's lien was properly recorded within the statutory 90-day deadline and how the lien would rank against the
-
314 So. 2d 643·
Fla. 4th DCA·
1975-06-20
·cited 2×
Industrial Supply Corporation appealed a summary judgment granted against it in a mechanic's lien foreclosure action. The court reversed, holding that a materialman furnishing materials to a sub-subcontractor who complies with statutory procedural requirements is entitled to a me
-
268 So. 2d 369·
Fla.·
1972-10-25
·cited 2×
The court held that a materialman is not entitled to a personal money judgment against a general contractor under the mechanics' lien law absent a contract, privity, or other statutory basis.
-
463 F.2d 413·
10th Cir.·
1972-07-13
·cited 2×
A cotenant cannot recover from other cotenants for unilateral improvements made without their consent or knowledge, and a party seeking contribution for partnership debts must properly present claims against an estate.
-
463 F.2d 929·
D.C. Cir.·
1972-03-28
·cited 2×
The court held that a personal money judgment entered against a defendant for failing to comply with a court order and after default was valid, even though the amount of the mechanic's lien against the property was later determined to be less.
-
250 So. 2d 324·
Fla. 4th DCA·
1971-06-25
·cited 2×
M & M Investments appeals a trial court judgment awarding money damages on a cross-claim that pleaded only equitable relief (mechanic's lien or equitable lien). The court reversed, holding that a trial court cannot award purely legal relief when only equitable relief is pled and
-
195 So. 2d 237·
Fla. 3d DCA·
1967-02-14
·cited 2×
Triangle Distributors challenged the dismissal of Travelers' Indemnity Company, a surety on a mechanic's lien bond, from an action to enforce the lien. The court held that a 1965 amendment to Florida's Mechanic's Lien Statute expanded the rights of lienors to sue sureties directl
-
The court held that an owner who pays a contractor after receiving notice of a materialman's lien is liable for the lien amount up to the sum paid after notice, even if it results in the owner paying twice.
-
353 F.2d 550·
9th Cir.·
1965-10-29
·cited 2×
The court held that a mechanic's lien was timely filed and that a trust deed was not subject to a subordination agreement procured by fraud, affirming the lower court's judgment.
-
A surety on a mechanic's lien undertaking is not liable merely because the lienor obtained a personal judgment against the principal owner; the lienor must show the owner had an interest to which the lien could attach, and the record did not support estoppel.
-
175 So. 2d 96·
Fla. 3d DCA·
1965-05-11
·cited 2×
This case involves an appeal from a mechanic's lien foreclosure action. The appellate court affirmed the lower court's decision, finding that the contractor had properly filed the necessary notices, including a lis pendens, and that the amount awarded was supported by substantial
-
309 F.2d 712·
10th Cir.·
1962-11-05
·cited 2×
The court held that aerial spraying services do not constitute labor or materials for the erection, alteration, or repair of a building or structure, thus not creating a statutory mechanic's lien. Attorney fees awarded in connection with the invalid lien were also reversed.
-
132 So. 2d 310·
Fla. 2d DCA·
1961-08-11
·cited 2×
Poston Steel Erection sued to foreclose a mechanic's lien for work performed hauling and erecting precast concrete beams. The trial court found Poston negligent in handling the fourth beam, which buckled and became worthless, and awarded only the contract balance minus the replac
-
117 So. 2d 416·
Fla. 3d DCA·
1960-01-25
·cited 2×
Amatrudi appeals from an order dismissing his complaint for foreclosure of a mechanic's lien against the equitable interest of the Blakes in real property held in trust. The Third District Court of Appeal holds that a mechanic's lien may attach to an equitable interest in land, r
-
94 So. 2d 178·
Fla.·
1957-01-04
·cited 2×
A decorator sued to foreclose a lien for decorative work and materials provided to a restaurant/lounge property leased by his employer. The Florida Supreme Court reversed summary judgment, holding that decorative improvements performed by a lessee in accordance with lease obligat
-
192 F.2d 978·
8th Cir.·
1951-12-12
·cited 2×
The court held that the mechanic's lien filed by appellee was prior and superior to the mortgage lien of the appellant because the appellee had a valid statutory lien before the mortgage was executed and the appellant had sufficient notice of the appellee's claim.
-
In this mechanic's lien enforcement case, the Florida Supreme Court affirmed a judgment for the plaintiff who performed labor on a steam saw mill, rejecting the defendant's challenges to the sufficiency of the affidavit, the constitutionality of the mechanic's lien statute, and t
-
391 So. 3d 426·
Fla. 4th DCA·
2024-05-15
·cited 1×
Defendants were the prevailing party on the significant issues in the litigation for purposes of attorney's fees under the subcontracts' prevailing party provision because they defeated most of Subcontractor's claimed damages, even though Subcontractor obtained a partial affirmat
-
Jon M. Hall Company sought certiorari review of a circuit court order granting partial summary judgment in favor of Canoe Creek on Hall's construction lien foreclosure claim and denying Hall's motion to amend its complaint to add the bond surety as a defendant. The court held tha
-
226 So. 3d 935·
Fla. 4th DCA·
2017-08-30
·cited 1×
Homeowners appealed the trial court's denial of their motion to release a lien transfer bond after they properly followed statutory procedures to contest a mechanic's lien. The court reversed, holding that when homeowners comply with Florida's statutory scheme for lien transfer b
-
The Jameses appealed summary judgment entered in favor of Pneuma Construction and Jones on a counterclaim for breach of contract and construction lien foreclosure. The appellate court reversed because the conflicting affidavits created genuine issues of material fact that preclud
-
National City Bank appeals a trial court's denial of its motion to reconsider a default judgment on the grounds that it was denied due process to contest unliquidated damages. The Fourth District reverses, holding that the appellate court's prior reversal on the excusable neglect
-
The court held that summary judgment was proper because there were no genuine issues of material fact and the moving party was entitled to judgment as a matter of law.
-
23 So. 3d 862·
Fla. 3d DCA·
2009-12-16
·cited 1×
SAAD Homes appealed the denial of its motion to dismiss or transfer venue in a breach of contract action filed in Miami-Dade County. The court reversed, holding that venue was improper in Miami-Dade County because the property and lien foreclosure action were located in Broward C
-
In this construction contract dispute, the trial court entered judgment for the contractor despite a jury verdict awarding zero damages on all claims. The appellate court reversed, holding that the contractor waived any challenge to the inconsistent verdict by failing to object b
-
Chapter 558, Florida Statutes, does not preclude the assessment of damages as a set-off under case law when a party to a construction contract does not strictly comply with the statute's provisions, as the statute's sole remedy for noncompliance is abatement.
-
A business organization is considered licensed if it has a qualifying agent responsible for its projects, even if its certificate of authority application was not yet filed. The court denied summary judgment.
-
The court held that the summary judgment motion did not provide sufficient notice that it applied to the construction lien claim, violating procedural rules.
-
687 So. 2d 282·
Fla. 1st DCA·
1997-01-16
·cited 1×
Pellar and Sweetwater appealed a trial court's reduction of their claimed appellate attorney's fees from $10,351.51 to $2,844.61. The court affirmed, holding that the trial court did not abuse its discretion in setting a reasonable fee amount for an uncomplicated appeal where the
-
533 So. 2d 879·
Fla. 4th DCA·
1988-11-02
·cited 1×
-
532 So. 2d 710·
Fla. 5th DCA·
1988-09-01
·cited 1×
The court held that the supplier of stucco was a merchant and thus provided an implied warranty of merchantability to the buyer, even if the buyer was not in privity with the supplier.
-
659 F. Supp. 138·
S.D. Fla.·
1987-04-24
·cited 1×
The court held that it lacks subject matter jurisdiction over claims against an insolvent thrift association in FSLIC receivership, requiring parties to pursue administrative remedies first.
-
464 So. 2d 1320·
Fla. 5th DCA·
1985-03-14
·cited 1×
A materialman sought to foreclose a mechanic's lien for materials supplied to a contractor improving leased property. The trial court dismissed the action for failure to allege delivery of the claim of lien, denying the materialman's oral motion to amend. The appellate court reve
-
393 So. 2d 648·
Fla. 5th DCA·
1981-02-11
·cited 1×
The appellate court affirmed the trial court's attorney's fee award, finding no clear showing of abuse of discretion.
-
341 So. 2d 823·
Fla. 3d DCA·
1977-01-25
·cited 1×
Paul Vaughan appeals a final judgment awarding Art Construction Company $106,652.28 plus attorney's fees and foreclosing a mechanic's lien on his property for unpaid construction costs. The Third District Court of Appeal affirmed, holding that the contractor complied with statuto
-
196 So. 2d 486·
Fla. 3d DCA·
1967-03-14
·cited 1×
The court held that a surety is a proper party in a mechanic's lien foreclosure action where a bond has been substituted for the lien, and that the defense of duress by business compulsion was properly stricken because the defendants had an adequate remedy at law.
-
142 So. 2d 754·
Fla. 3d DCA·
1962-06-26
·cited 1×
The court held that a mechanic's lien for architectural services requires proof that the services or plans were actually used in improving the real property, and a valid release of lien is effective.
-
The trial court's award of $9,596 to Sarbu Construction for substantial performance of a change order is affirmed. However, the determination that Sarbu Construction was the prevailing party is reversed because the trial court applied an incorrect test; the proper test requires c
-
A party seeking a trial de novo following non-binding arbitration complies with Florida Rule of Civil Procedure 1.820(h) when it timely files a document that provides notice of rejection of the arbitration decision and requests a trial de novo, even if the document does not expre