149 Florida cases classified under this topic, plus 500 listed through its narrower topics · sorted by citation count · see the citation graph · browse and sort
-
The appellate court held that the trial court improperly refused to rule on pending motions after an appeal was dismissed, as jurisdiction was reactivated.
-
A mechanic's lien statement that fails to describe the labor and materials furnished is insufficient under Wyoming law, even under the 'lump sum' rule, and is not enforceable against a bankruptcy trustee.
-
Surfside Estates appealed a judgment in which a jury awarded punitive and special damages to Waterway Homes on a counterclaim for fraudulent lien filing. The issue was whether the trial court erred in admitting the final judgment from the foreclosure proceeding into evidence at t
-
-
Hazel Barth appealed a judgment in favor of Florida State Constructors Service on her counterclaim for poor workmanship, arguing the trial court committed reversible error by instructing the jury on the law before closing arguments rather than after. The court held that while suc
-
Coplan Pipe & Supply Co. appeals from a summary judgment dismissing its mechanics lien foreclosure suit based on collateral estoppel arising from an adverse jury verdict in a separate breach of contract action. The court reverses, holding that collateral estoppel does not apply b
-
Florida City Development Corporation appealed the trial court's denial of attorney's fees in a case where it prevailed on a mechanic's lien counterclaim. The appellate court reversed, holding that under Florida Statute § 713.29, the prevailing party in a mechanic's lien action is
-
Acco, Inc., a heating-air conditioning contractor, appealed summary judgment in favor of Biscayne Federal Savings and Loan Association in a foreclosure action where Acco was not joined but was later compelled to exercise redemption rights. The court reversed, holding that Acco's
-
-
The recording of a notice of lis pendens bars the enforcement of an unrecorded mechanic's lien, even if the lien would otherwise relate back to an earlier notice of commencement.
-
-
The Weaners appealed the dismissal of their third-party complaint against the Regars in a construction dispute. The court affirmed the dismissal, holding that the Weaners had no viable claim against the Regars for breach of a covenant against encumbrances because any mechanic's l
-
The court held that the rental cost of a rock crusher, not used in construction, could not be included in a mechanic's lien, and the reasonable rental value of machinery must be based on actual work performed, not just contract duration.
-
-
-
-
Appellants Boston appealed an order denying their motion to dismiss a mechanic's lien foreclosure complaint, arguing the lienor failed to institute suit within 60 days as required by statute. The court affirmed the denial of the motion to dismiss, holding that the timeliness defe
-
-
Defendant-appellants appealed an interlocutory order denying their motion to dismiss a mechanic's lien foreclosure action. The court affirmed the denial, holding that at the motion to dismiss stage, the complaint's allegations of statutory compliance are sufficient and factual de
-
The court held that the trial court erred in denying the appellants' motions to dismiss the petition for declaratory relief because the petition failed to state a justiciable cause of action against them.
-
Adobe Brick and Supply Company sought to foreclose a mechanics' lien against a property owner for unpaid materials supplied to a subcontractor. The trial court dismissed the case based on an alleged error in the property description in the lien claim. The appellate court reversed
-
A supplier of drywall materials (Adobe Brick) sought to enforce a mechanic's lien against property owner Port Royale Apartments and contractor First General Contractors. The trial court found $11,697.26 due to the supplier and affirmed that judgment, rejecting claims for material
-
The court held that the owner established damages for certain construction defects under the cost of repair rule, but other defects were not subject to this rule due to economic waste. The contractor was entitled to reimbursement for change orders.
-
The court held that the subcontractor's mechanic's lien rights are preserved and will not be lost due to the passage of time, despite the Chapter X reorganization proceedings.
-
A fee title owner appealed a judgment imposing personal liability and a mechanic's lien on both its legal title and the equitable interest of purchasers under an agreement for deed. The court reversed, holding that the fee owner cannot be personally liable for repairs contracted
-
A materialman brought a mechanic's lien foreclosure against property owners who were not in privity with the materialman. The owners challenged the validity of the lien and sought to offset damages from a subcontractor's breach of contract. The court affirmed the judgment in favo
-
The court held that Prepakt was entitled to interest on its mechanics lien claim but not on its contract claim, and that a bond premium was not a covered cost under the labor and material bond.
-
The court affirmed the granting of a default judgment against a defendant who failed to file an answer within the time ordered by the court, despite filing an answer and counterclaim shortly after the default was entered.
-
204 So. 2d 357·
Fla. 2d DCA·
1967-11-15
The court held that the defendant's appeal lacked merit and affirmed the judgment and sentence.
-
A materialman sought to foreclose a mechanic's lien for materials incorporated into a construction project. The court denied the defendant-owner's motion for summary judgment, holding that the failure to serve notice of lien within 45 days does not automatically bar the lien if n
-
Russell, Inc. sought to foreclose a mechanic's lien against the Opers for landscaping services provided to their residence. The court upheld the lien despite defendants' challenge that plaintiff failed to provide a sworn statement as required by Florida statute, finding that dire
-
Maule Industries appealed a summary judgment denying its mechanic's lien foreclosure action on the ground that its lis pendens failed to strictly comply with statutory requirements. The Fourth District Court of Appeal reversed, holding that the lis pendens achieved substantial co
-
A mechanics' lien case involving whether a sewerage treatment system's equipment can be subject to a mechanic's lien when the contractor had no interest in the underlying land. The court held that the equipment is removable under Florida law and remanded for the trial court to im
-
The court held that the attorney had authority to execute releases and that the releases did not contravene public policy, were supported by consideration, and the pre-trial order was properly modified.
-
In this equity case, the trial court dismissed plaintiff's third amended complaint for failing to allege a cause of action in equity and transferred the case to the law side with leave to file an amended complaint. The defendants appealed the transfer, arguing the plaintiff canno
-
A party in possession of land under a contract to purchase is not considered an 'owner' for the purpose of impressing a mechanic's lien. A settlement payment from the landowner to the trustee was for 'peace' and not a purchase of the bankrupt's interest.
-
Appellants appealed from a foreclosure decree on a mechanic's lien for swimming pool and patio construction work. The trial judge awarded the contractor $3,800, finding the work was substantially performed but required approximately $700 in repairs to complete properly.
-
Materials are considered 'specially fabricated' for a mechanic's lien only if they have little value if not used for the particular improvement.
-
The court held that the parties are bound by their agreement to conduct arbitration under the American Arbitration Association rules, which do not require detailed findings of fact or conclusions of law for an award to be entered as a judgment.
-
The court held that parol evidence was inadmissible to explain a written waiver of lien, and the refusal to transfer the case to the law side was proper because a complete defense to the lien was proven.
-
The Florida Supreme Court affirmed a lower court's decision voiding a note and mortgage due to usury. The court found that the lender willfully and knowingly charged excessive interest, forfeiting the entire principal and interest as per state statute.
-
In this mechanics' lien case, the Florida Supreme Court reversed a motion to dismiss and held that a contractor who performed demolition and salvage work on property owned as an estate by the entireties could establish a valid mechanics' lien without providing notice to the non-o
-
196 F.2d 630·
4th Cir.·
1952-05-02
A materialman's lien is valid against multiple houses in a single project even if specific materials cannot be traced to each house, provided the project was treated as an entirety by the parties.
-
A plaintiff is entitled to amend a mechanic's lien foreclosure bill to allege compliance with statutory notice requirements, even after testimony has been taken, if the amendment concerns a procedural right and no inequity results.
-
The court held that the appellee, having purchased the property for value without notice, is a bona fide purchaser, and the appellants' claims are barred by their delay and failure to act.
-
This case concerns a subcontractor's attempt to foreclose a lien for unpaid work on an ice plant. The appellate court reviewed whether certain costs incurred by the owner to complete the plant were contemplated by the original contract, thus reducing the amount owed to the origin
-
Roth sought to enjoin execution on a judgment by setting off a debt owed to him by the Bowmans under a lease. The Florida Supreme Court held that a plea of set-off cannot be used as an equitable defense in a common law action, reversing the lower court's dismissal of the bill of
-
97 Fla. 1077·
Fla.·
1928-04-26
Clark Dredging Co. appealed the dismissal of its bill of complaint seeking to enforce a materialman's and laborer's lien for dredging and fill work performed on submerged and marsh lands owned by Sunny Isles Ocean Beach Co. The Florida Supreme Court reversed, holding that dredgin