FISHER ISLAND HOLDINGS, LLC, A LIMITED LIABILITY COMPANY ORGANIZED UNDER THE LAWS OF THE STATE OF FLORIDA, APPELLANT,
v.
JOEL COHEN AND RITA COHEN, HIS WIFE, APPELLEES
AI-generated. These summaries, headnotes, and key points are machine-generated and may contain errors or omissions. Always verify against the full opinion text below. Not legal advice.
Fisher Island Holdings appeals a jury verdict awarding the Cohens damages for both construction delay and alternative living arrangements after their home was not completed on schedule. The court affirmed, finding no impermissible double recovery because the damage awards covered non-overlapping time periods.
The court held that the damages do not constitute impermissible double recovery because the time periods for each award did not overlap. Delay damages were awarded through December 2006, while alternative living arrangement damages were awarded from January 2007 through September 2007, so there was no double recovery for any single period of time.
[1] A jury is empowered to determine the amount of damages to be awarded to an aggrieved party.
[2] Damages for delay in construction are measured by the rental value of the building under construction during the period of delay.
Previewing 2 of 4 headnotes on this case. FLexlaw’s editorially structured points of law — every proposition, pinpointed — are reserved for members.
Join FLexlaw to unlock all legal intelligence“It is within the province of the jury to determine the amount of damages to be awarded to an aggrieved party.”
Establishes that jury has discretion in calculating damage amounts and appellate court defers to jury verdict on damages.
Previewing 1 of 3 key quotes on this case — the court’s exact language, pinpointed for members.
Join FLexlaw to unlock all legal intelligenceThe Cohens contracted to purchase a Fisher Island home with construction to be completed by December 2004. Due to substantial construction delays, the…
The full statement of facts, procedural history, and disposition for this case are member content.
Join FLexlaw to unlock all legal intelligence© FLexlaw, Inc. — AI-generated enrichments are proprietary. All rights reserved.
Explore caselaw by topic → Browse Contract Damages cases and more on FLexlaw
[*1204] CORTINAS, J.
Joel and Rita Cohen (the “Cohens”) sued Fisher Island Holdings, LLC (“Fisher Island”) alleging breach of contract arising out of the construction and purchase of their Fisher Island home. The jury awarded the Cohens $708,147 in damages for the delay in construction and $144,000 for alternative living arrangements. Fisher Island appeals the jury’s award of damages for alternative living arrangements. We affirm.
The construction of the Cohens’ home was to be completed no later than two years from the signing of the Agreement for Sale on December 4, 2002. Thus, the closing should have occurred shortly after December 2004. As a result of substantial delays in construction, sometime in late 2006 the Cohens entered into a nine-month lease (“Lease”) in the amount of $144,000 for alternative living arrangements commencing in January 2007 and ending September 2007.* During trial, the court granted the Cohens’ directed verdict as to liability for the delay in construction, leaving it to the jury to determine the amount of damages the Cohens were to receive.
Fisher Island argues that the jury’s award of damages for the delay and alternative living arrangements constitutes impermissible double recovery. We disagree. It is within the province of the jury to determine the amount of damages to be awarded to an aggrieved party. Koine v. Gov’t Employees Ins. Co., 735 So. 2d 599, 600 (Fla. 3d DCA 1999). Damages for delay in construction are measured by the rental value of the building under construction during the period of delay. Russo v. Heil Constr., Inc., 549 So. 2d 676, 677 (Fla. 5th DCA 1989); Vanater v. Tom Lilly Constr., 483 So. 2d 506, 508 (Fla. 4th DCA 1986).
The jury calculated the delay damages based upon the fair market net rental value of the home and awarded delay damages through December 2006. Fisher Island objected only on grounds that the damages proposed by the Cohens were duplicative. Importantly, Fisher Island never objected to the proper measure of damages and, thus, did not preserve this issue for appeal. Tribble & Stephens Co. v. Consol. Sens., Inc., 744 S.W. 2d 945, 949 (Tex.App.1987) (“Appellants failed to raise the issue of an improper measure of damages in the trial court and thus waived review of their complaint.”). Damages for alternative living arrangements, based on the Cohens’ lease, were awarded from January 1, 2007 through September 2007.
We address the only issue preserved on appeal. While we agree that a party may not receive double recovery for the same breach of contract, we find that the damages awarded did not constitute impermissible double recovery. See Tillman v. Howell, 634 So. 2d 268, 271 (Fla. 4th DCA 1994) (stating that recovery for the cost of moving, storage, and living quarters plus an award for the fair rental value of a home under construction constituted double recovery). Because the time-frame for each award of damages did not overlap and there was no double recovery for any one period of time, the damages awarded to the Cohens are not duplicative. Accordingly, we uphold the jury’s award of damages for alternative living arrangements.
Affirmed.
*
Fisher Island did not object to this evidence and also did not object to the verdict form allowing damages for alternative living arrangements.
Cases With Similar Vibessemantic neighbors from the corpus
Citator
Cited By
-
Gonzalez v. Barrenechea, 170 So. 3d 13 (Fla. 3d DCA 2015)…ntoni, 801 So. 2d 990 (Fla. 2d DCA 2001); Taylor v. Lee; 884 So. 2d 222 (Fla. 2d DCA 2004) ("[it] is incumbent upon the party seeking damages to present evidence to justify an award of damages in a definite amount”); Fisher Island Holdings v. Cohen, 983 So. 2d 1203 (Fla. 3d DCA 2008) (holding it is in the province of the finder of fact to determine the amount of damages). . The majority asserts the trial court stated that “the appraiser purportedly admitted that there was no market for the subject property,”…1 / 2
-
Action Nissan, Inc. v. Hyundai Motor Am., 617 F. Supp. 2d 1177 (M.D. Fla. 2008)…ce of any damages resulting from the unfair system of distribution. Generally, so long as Plaintiff has produced some evidence of its injury, the factual determination of damages is one for the jury. E.g., Fisher Island Holdings, LLC v. Cohen, 983 So.2d 1203, 1204 (Fla. 3d DCA 2008). Plaintiff has offered evidence of the injury it claims resulted from Defendant’s violation of the DPA. For instance, Plaintiff has produced the sworn statement of Mr. Nero, Plaintiffs owner and operator, in which he states:…
Authorities Cited
- Russo v. Heil Constr., Inc., 549 So. 2d 676 (Fla. 5th DCA 1989)
- Vanater v. TOM Lilly Constr., 483 So. 2d 506 (Fla. 4th DCA 1986)
- Tillman v. Howell, 634 So. 2d 268 (Fla. 4th DCA 1994)
- Kaine v. Gov't Emps. Ins. Co., 735 So. 2d 599 (Fla. 3d DCA 1999)